Construction crews are working on several road construction projects around Denton. Take a look at five road project updates around town. This list is not comprehensive.
Alice Street reconstruction
Project: The project will replace the waterline, curb, gutter and portions of the sidewalk along Alice Street. The project’s scope also includes a total roadway reconstruction. This project is funded from the $50 million Neighborhood 2 bond approved by voters in 2019.
Update: Crews are nearly complete with concrete work with final paving scheduled for late April.
- Timeline: September 2025-June
- Cost: $1.46 million
- Funding source: city of Denton
Wellington Drive reconstruction
Project: Crews will replace the waterline, curb, gutter and portions of the sidewalk, as well as total reconstruction of the roadway. This project is funded from the $26 million Neighborhood 1B bond approved by voters in 2019.
Update: Workers began construction on roadway demolition and earth work in mid-April.
- Timeline: September 2025-June
- Cost: $707,324
- Funding source: city of Denton
Buckingham Drive reconstruction
Project: Construction work includes replacing the waterline, curb, gutter and portions of the sidewalks along Buckingham Drive. The project’s scope also includes a total roadway reconstruction and is funded from the $26 million Neighborhood 1B bond approved by voters in 2019.
Update: Utility work is nearly complete on the south end of the project and crews have started on road demolition on the north end.
- Timeline: November 2025-June
- Cost: $1.18 million
- Funding source: city of Denton
Bonnie Brae Street Phase 6
Project: Workers will widen the road with two additional lanes and a pedestrian and bike path alongside the road. The phase is part of a multi-year seven-phase expansion project.
Update: Contractors began work to modify the soil in preparation for the roadway expansion at the northern part of Bonnie Brae Street.
- Timeline: January 2025-April 2027
- Cost: $38 million
- Funding sources: city of Denton, Denton County
Mulberry Street waterline extension
Project: Contractors are replacing the water line along West Mulberry Street to accommodate a future multifamily development. Workers are replacing the 4-inch waterline with an 8-inch waterline to increase capacity.
Update: The road between Carroll Boulevard and Locust Street closed for construction on April 8, according to a city staff report.
- Timeline: April-June
- Cost: $199,764
- Funding sources: City of Denton, Mulberry Apartments
Huntington Drive improvements
Project: The work included replacing the waterline, curb, gutter and portions of the sidewalk, as well as total reconstruction of the roadway. This project is funded from the $26 million Neighborhood 1B bond approved by voters in 2019.
Update: Workers completed construction on the road segment and the road reopened in late March.
- Timeline: October 2025-March
- Cost: $754,358
- Funding source: city of Denton
Westgate Drive Connector
Project: The project connects Bronco Way to Westgate Drive, giving it access to the I-35 service road.
Update: Construction wrapped on the project in April, according to an update from city staff to city council and Denton ISD board of trustees.
- Timeline: August 2025-April
- Cost: $3.91 million
- Funding source: city of Denton
Sheraton Road improvements
Project: Crews replaced the waterline, curb, gutter and portions of the sidewalk and the entire roadway was reconstructed. This project is funded from the $26 million Neighborhood 1B bond approved by voters in 2019.
Update: Workers completed construction on the road segment and the road reopened in late March.
- Timeline: August 2025-March
- Cost: $1.41 million
- Funding source: city of Denton