Check out the latest updates on three ongoing construction projects in Richardson, per the city's capital projects tracker.
1. Lakeside Boulevard reconstruction
Project: Crews are reconstructing the street and implementing utility improvements on Lakeside Boulevard from US 75 to Campbell Road, and Lawnview Drive from Lakeside to Greenville Avenue.
Update: Installation of the waterline sewers from the roundabout to Campbell is currently underway, along with work in the Lawnview median.
- Timeline: winter 2024-spring 2026
- Cost: $10 million
- Funding source: 2021 bond
2. Glenville Drive reconstruction
Project: The work includes pavement reconstruction along with improvements to public utilities, traffic signals, lighting, pedestrian sidewalks and bike lanes.
Update: The main southbound lane reopened to traffic March 20, and crews are currently working on sidewalks, bike lanes and other improvements at Glenville’s intersection with Arapaho Road.
- Timeline: winter 2021-spring 2026
- Cost: $23.7 million
- Funding sources: 2015 and 2021 bonds, City of Richardson, grants
3. Sherman Street reconstruction
Project: This project consists of road reconstruction of Sherman Street from Kaufman Street to Lingco Drive and reconstruction of Lingco from Sherman to Spring Valley Road.
Update: Crews have completed underground utility work and paving work on the northbound lane. Work at the intersection of Lingco and Spring Valley was set to finish in March.
- Timeline: winter 2023-summer 2026
- Cost: $6.55 million
- Funding source: 2021 Bond