Project: Sunset Boulevard is being repaved, and a sanitary sewer is being installed from Preston Road to Coit Road. The project has seen some delays.
Update: The contractor for the project is wrapping up work with repairing irrigation, according to Celina’s capital improvement site.
- Timeline: estimated completion June 2026
- Cost: $4.2 million
- Funding source: city of Celina
10. Choate Parkway reconstructionProject: Choate Parkway is being reconstructed from the existing two-lane roadway to a six-lane divided roadway from Coit Road to Roseland Parkway. The project will be shared with the city and the adjacent subdivision developer.
Update: The project is divided into two phases. The first phase, which is about half a mile from Coit Road, is under construction. The second phase is delayed due to utility relocation and is expected to start construction this summer, according to Celina’s capital improvement site.
- Timeline: estimated completion December 2026
- Cost: $10.91 million
- Funding sources: city of Celina, adjacent developer