Interested in roadwork updates impacting McKinney residents? Here are updates on several planned roadway and infrastructure construction projects in McKinney.
This list is not comprehensive.
1. Industrial Boulevard utility improvements
Project: The planned reconstruction of existing water and sanitary sewer lines will take place along Industrial Boulevard between SH 5 and Airport Drive.
Update: Design work is 90% complete, and the project is expected to go to bid later this year.
- Timeline: late 2026-late 2027
- Cost: $9.2 million
- Funding source: city of McKinney
2. SH 5 utility relocationsProject: Construction work will relocate city utilities, including water and wastewater lines, in advance of the planned reconstruction and widening of SH 5 by the Texas Department of Transportation. The second phase of the project will take place along SH 5 between SH 121 and Powerhouse Street.
Update: Design work is 90% complete, and the project is expected to go to bid later this year.
- Timeline: late 2026-late 2028
- Cost: $27.7 million
- Funding source: city of McKinney, TxDOT reimbursement
3. East Virginia Street improvementsProject: Reconstruction work is planned for East Virginia Street between Murray Street and Airport Drive, which will include a new alignment and connection to Airport Drive. A roundabout will also be constructed at the intersection of the realigned East Virginia Street and Lively Hill Lane. The project will also include improvements to water lines, sanitary sewer and storm sewer lines, illumination, hardscaping and landscaping.
Update: Design work is 90% complete, and the project is expected to go to bid later this year.
- Timeline: late 2026-late 2028
- Cost: $15 million
- Funding source: city of McKinney
4. Silverado Trail expansionProject: Construction will add westbound lanes to Silverado Trail between Kenley Drive and Burnett Drive. The project will also include construction of a bridge over Rowlett Creek.
Update: Design work is 90% complete, and the project is expected to go to bid in early 2027.
- Timeline: spring 2027-spring 2028
- Cost: $5.7 million
- Funding source: city of McKinney
5. Couch Drive reconstructionProject: Reconstruction work is planned for Couch Drive between Harry McKillop Boulevard and Industrial Boulevard. The project will also include storm drainage improvements.
Update: Design work is 90% complete, but construction is postponed to allow for additional sanitary sewer capacity improvements to be incorporated into the project.
- Timeline: late 2027-late 2028
- Cost: $7 million
- Funding source: city of McKinney