Ongoing projects
1. Virginia and Throckmorton infrastructure improvements
Project: Reconstruction of Virginia Street between SH 5 and Murray Street, and Throckmorton Street between Lamar and Louisiana streets will take place. The project includes waterline, sanitary sewer, storm sewer, illumination, hardscape and landscape improvements, as well as a roundabout at the intersection of Virginia and Throckmorton streets.
Update: Virginia Street has been opened to traffic, and the project is substantially completed. Landscape installation is ongoing and will require short-term, localized lane closures.
- Timeline: March 2024-January 2026
- Cost: $14 million
- Funding source: city of McKinney
Project: Renewal of substandard infrastructure, including streets, drainage and utilities, will take place at various segments.
Update: Paving has been completed on Jones and Foote streets. Paving operations for Lela Street are expected to begin in January.
- Timeline: February 2025-summer 2026
- Cost: $7.5 million
- Funding source: city of McKinney
3. Medical Center Drive improvements
Project: Reconstruction and widening of Medical Center Drive between Frisco Road and Spur 399 as a four-lane divided roadway will take place. The road is currently three lanes, undivided.
Update: McKinney City Council awarded a construction contract for the project Sept. 16. Construction is expected to begin in January.
- Timeline: January-early 2027
- Cost: $5.2 million
- Funding Source: city of McKinney