Check out 10 upcoming and ongoing transportation projects in Frisco, according to the city's capital improvement website. This list is not comprehensive.

Upcoming projects

1. Hillcrest Road updates


Project: Hillcrest Road will be updated from SH 121 to Main Street, though specifics on the project are not yet available.

Update: The project is in the planning phase.
  • Timeline: fall 2027-end of 2028
  • Cost: $12 million
  • Funding source: city of Frisco
2. John Hickman Parkway construction


Project: John Hickman Parkway will be expanded from Dallas North Tollway to Parkwood Boulevard.

Update: The project is in the planning phase, with construction expected to begin in 2027.
  • Timeline: early 2027-mid 2028
  • Cost: $5 million
  • Funding source: city of Frisco
3. Warren Parkway construction

Project: Warren Parkway is being updated from Legacy Drive to Internet Boulevard.

Update: Specifics are not yet available on the project, and it is in the planning phase.
  • Timeline: end of 2026-end of 2027
  • Cost: $4.2 million
  • Funding source: city of Frisco
Ongoing projects


4. PGA Parkway construction


Project: PGA Parkway is being constructed into a six-lane divided roadway from Preston Road to Coit Road.

Update: The project is under construction and expected to be completed near the end of next year.
  • Timeline: end 2024-September 2026
  • Cost: $31.1 million
  • Funding sources: city of Frisco, external funding
5. US 380 lighting installation

Project: US 380 is having street lights installed from the Denton and Collin counties line to Lovers Lane.


Update: The project is nearing the end of construction.
  • Timeline: early 2024-early 2025
  • Cost: $2.4 million
  • Funding source: external funds
6. Mahard Parkway construction

Project: Mahard Parkway is being constructed, and it will be six lanes. The roadway will span PGA Parkway to US 380 and will border the Firefly Park development.

Update: The project is under construction and is expected to be completed at the end of next year.
  • Timeline: late 2024-late 2026
  • Cost: $11.03 million
  • Funding source: city of Frisco
7. Teel Parkway widening

Project: Teel Parkway is being widened from Stafford Middle School to Olive Branch Drive. It is being widened from a two-lane divided roadway to a four-lane divided roadway.


Update: The project is under construction, which started this fall.
  • Timeline: fall 2025-end of 2026
  • Cost: $9.36 million
  • Funding sources: city of Frisco, external funding
8. Lebanon Road widening

Project: Lebanon Road is being widened from a four-lane divided roadway to a six-lane divided roadway. The project will span FM 423 to Todd Drive.

Update: The project is under construction.
  • Timeline: fall 2025-end of 2027
  • Cost: $23 million
  • Funding sources: city of Frisco, external funding
9. Hillcrest Road construction

Project: Hillcrest Road from Panther Creek Parkway to PGA Parkway is being constructed into a four-lane divided roadway.


Update: The project is under construction and is expected to be a few months from completion.
  • Timeline: early 2024-early 2026
  • Cost: $5.99 million
  • Funding source: city of Frisco
10. Mahard Parkway intersection installation

Project: A new traffic light is being installed at the PGA Parkway and Mahard Parkway intersection.

Update: The project is under construction, and it should be completed by the end of the year.
  • Timeline: early 2025-end of 2025
  • Cost: $300,000
  • Funding source: city of Frisco