Design work could begin as late as June, and roadway construction could begin as early as April 2021.
Timeline: April 2020-March 2021 (design), April 2021-March 2022 (construction)
Cost: $5.6 million
Funding source: city of Frisco
Design work for the project could begin as late as June. (Courtesy Fotolia)