Check out these two road construction projects recently completed or ongoing in Argyle.
Ongoing
1. Frenchtown Road maintenance repairs
Project: Removing and replacing 400 feet of damaged pavement on the westbound side only.
Update: The road will be controlled by a temporary traffic signal between Caublestone Drive and Manor Drive.
- Timeline: July 14-28
- Cost: $45k
- Funding source: town of Argyle street maintenance fund