Lewisville ISD trustees approved $15.4 million in campus construction projects at a March 9 board meeting, following a March 2 report from Executive Construction Director Randy Fite.
By the numbers
The projects include:
- $434,904 for new shade structures at Timber Creek Elementary School
- $80,057 for a new marquee at Timber Creek Elementary School
- Nearly $9.08 million for Highland Village Elementary playground and paving improvements and various LISD programs
- Almost $2.53 million for the Lewisville High School baseball concessions replacement
- Close to $1.17 million for The Colony High School indoor athletic center upgrades
- $1.09 million for the Lewisville High School boys track locker room renovation
- Over $1 million for Lewisville High School indoor athletic center upgrades
Zooming in