Progress is continuing on Leander ISD's next two elementary schools after the board of trustees approved the maximum guaranteed construction costs for both projects Nov. 12.
The limits were approved in a 4-2 vote, with trustees Sade Fashokun and Paul Gauthier dissenting. Trustee Trish Bode was not present.
Elementary 31 has an approved construction cost limit of $66.7 million, while Elementary 32 has a limit of $62.8 million.
Some context
Elementary 31 and 32 were both approved under Proposition A in the 2023 bond.
Elementary 31 is intended to add capacity in the northeast part of the district, including the Tarvin, Parkside and Akin elementary feeder area.
At the Oct. 1 board meeting, Chief Operations Officer Jeremy Trimble presented a plan that would relocate the existing Mason Elementary community to Elementary 32, which will be built within the Travisso community.
According to district data, only 24% of students zoned to Mason live in its immediate area, while 51% live within the Travisso corridor and another 25% in surrounding areas.
The discussion
Over 50 community members signed up to speak during the Nov. 12 board meeting. Many urged the board to deliver on its promises from the 2023 bond by building both campuses, and spoke in favor of relocating Mason Elementary students to the new No. 32 campus.
"Placing a new school facility in Travisso will go a long way toward making LISD a competitive choice for those families," said Maggie Moore, a Mason Elementary parent and Travisso resident. "I know, because I've talked to many friends and neighbors who said plainly that a neighborhood school would have made staying in the district an obvious choice for them."
Others spoke against the proposed relocation and new campus. Mason Elementary parent Jenna Edge said the existing Mason campus is a "neighborhood school," and that demographic projections do not justify building No. 32.
"Our district is at the end of the plateau; downward trend is next," Edge said. "Every resident living west of Mason, including parents that drive their kids to charter or private schools, drive east on 1431 everyday at least twice a day. ... [Mason's] current location is perfect."
The action taken
The board ultimately approved Elementary 31 and 32's construction cost limits, effectively pushing construction forward for both campuses to open by the 2028-29 school year.
Trimble noted that both projects have already experienced delays. No. 31 initially had an opening date of 2025-26, and No. 32 in 2027-28.
Any further delays would impact the district's ability to ensure delivery of both within the allocated budget, Trimble said. No. 32 specifically faced delays due to shifting enrollment patterns.
"[In 2024] the traditional methods in which we approached the planning for schools was a little bit different than what we're bringing here today," Trimble said. "Mason was going to be very large, and so No. 32 was going to be able to address some of that growth. As that growth started to slow down and that trajectory of Mason looked a little bit different, that's when No. 32 planning was slowed down."
Fashokun, who voted against the cost limits, voiced concerns with enrollment projections—largely due to private or charter schools—that could lead to future underenrolled campuses.
"We've seen neighborhood schools end up being underenrolled to the point where we're talking about consolidation," Fashokun said. "With these numbers ... it could accelerate to where one or both of these, in five years, we'll be having those discussions."
Conversely, trustee Gloria Gonzalez-Dholakia said that many of LISD's schools have been built "where kids are."
"When we tell our community we're passing a bond and these are the things we're going to do with that bond, and then we say, 'Oh, we're going to do a switcheroo; we're going to change it,' why would anyone in that community ever trust you for a bond ever again?" Gonzalez-Dholakia said. "What hasn't changed is there's a lot of growth in these areas."
Something to note
The board was previously slated to vote on the maximum construction costs at its regular meeting Nov. 19, which would have taken place after incumbent Laura Marques and new trustees Serenity Coats and Chitra Nedun were sworn in.
Trustee Anna Smith said the board attorney recommended a special meeting be held prior to this, amid concerns about newly seated trustees voting on the matter at their first meeting.