The Leander Independent School District board of trustees moved forward with plans to use leftover bond funds to make capital improvements at three campuses at its March 1 meeting.
Galvanized steel water pipes at Cedar Park High School and Naumann Elementary School have been leaking due to corrosion, said Jimmy Disler, executive director of capital improvements.
The board approved staff's recommendation to hire a construction manager at risk to oversee replacement of the pipes. The cost will not exceed $500,000 and will commence as soon as this summer, according to district documents.
Funding for the replacement pipes—which will be made of PVC, copper or another noncorrosive material—will come from $1.1 million in bond money saved from the Whitestone HVAC replacement project.