College Station ISD estimates it has nearly $16 million in remaining funds from its 2024 athletic bond, and district officials are considering using the money for additional improvements at both high schools. (Karley Cross/Community Impact)
College Station ISD estimates it has nearly $16 million in remaining funds from its 2024 athletic bond, and district officials are considering using the money for additional improvements at both high schools.
The overview
During their Nov. 17 board workshop, Assistant Superintendent of Operations Josh Symank, alongside CFO Heather Wilson, outlined to trustees how the district completed the bond projects, where the remaining funds came from and what additional work could be funded. No spending decisions were made during the workshop nor the regular meeting.
How we got here
Voters approved the two athletic propositions in May 2024, providing about $53 million for improvements at College Station and A&M Consolidated high schools. The projects included a field house addition at Consol, renovations and upgrades at both football stadiums and artificial turf among other improvements at the high schools’ baseball and softball facilities.
All four major projects have been completed, with only a few minor items and equipment deliveries remaining, Symank said. He and Wilson estimated roughly $15.96 million in remaining funds, including interest income. Symank and Wilson clarified that the figure is preliminary and that final costs and payments still need to be settled.
Symank showed district material attributing the remaining funds to:
Competitive bidding
Keeping project scopes focused on needs
Completing work on an accelerated timeline
Working with local contractor Jacoby Construction
The district also avoided expanding stadium seating and restroom facilities after reviewing attendance and ticket-sale data, Symank said.
The options
Wilson told trustees the remaining funds could be used for projects allowed under the original bond propositions, applied toward outstanding debt or directed to other facility improvements through an additional approval process.
Bond funds cannot be used for routine operating expenses, such as employee salaries, utilities or supplies.
The district currently has about $536 million in outstanding debt, Wilson said. Applying the remaining funds toward debt payments could generate an estimated $98,000 in annual interest savings, but Wilson recommended placing the money toward debt payments scheduled for 2037 and 2040.
Instead, Symank and Wilson outlined a range of potential facility improvements. Possible options include:
Resurfacing tennis courts
Replacing turf in the future
Repairing the A&M Consolidated track
Upgrading other field houses
Another option laid out was installing basketball shot clocks. Symank said UIL will require shot clocks–which are countdown clocks–beginning in 2028.
Symank and Wilson outlined a range of potential facility improvements.Courtesy College Station ISD
The largest proposed addition would be a covered, multipurpose practice facility at each high school. Wilson and Symank estimated the two facilities together would cost about $6 million. Each would include about 70 yards of turf and could be used for athletics, band, fine arts and other student activities.
Symank showed trustees pictures of a similar facility in Rio Vista to give them an idea of how the facilities could look.
The largest proposed addition would be a covered, multipurpose practice facility at each high school.Courtesy College Station ISD
He said the covered spaces could help address disruptions caused by extreme heat. About 40% of outdoor practices between July and October were affected by wet-bulb temperature restrictions, he said.
“The day that we went and visited, the field turf that day was reading at 161℉, and when we walked into the facility, the field turf in there was reading at 90℉,” Symank said.
The facilities would provide shade and ventilation while allowing students to continue some activities outdoors.
What’s next?
The district estimated the full list of potential improvements could cost between $10 million and $10.5 million, though several projects still need more detailed estimates. Officials said they would bring more specific cost information to trustees at a later date.
To use remaining funds for projects outside the original bond purposes, the board would need to hold a public hearing and approve the proposed use. Symank said that process could take place next summer, followed by votes on individual projects.
Symank said the proposed work would use existing bond funds and would not require additional taxpayer funding.