In February 2019, League City officials celebrated the opening of the newly reconstructed Calder Road from League City Parkway to Ervin Avenue. They invited residents to a ribbon-cutting ceremony and handed out coffee and T-shirts that read, “I survived Calder Road construction.” But in truth, the road’s work was far from over.
In the fall of 2019, work began to reconstruct Calder Road from Ervin to Cross Colony Drive in the same way as the northern potion: The road would be widened from two lanes to three; one lane would become a continuous center-turn lane; and the road would be converted from asphalt with ditches on the sides to concrete with curbs and gutters.
Officials said the work on the southern portion is going much better than it did on the northern portion.
The northern work was a challenge, officials said, because it was essentially four projects in one: Contractors had to install a new water pump station, a new water line and a new sanitary sewer before road work could begin.