Balking at the amount of time it would take for construction to begin, League City City Council on Oct. 27 approved a contract that will result in a new eastbound right turn lane on League City Parkway onto the I-45 frontage road.
The right turn lane will begin 450 feet west of Butler Road and run past Calder Road to hook up with the Texas Department of Transportation right turn lane at the corner of League City Parkway and I-45.
Noticing the schedule for construction, Council Member Larry Millican asked how it would take a year for the engineering firm, JNS Engineers, to design the turn lane before construction would even begin.
Project Management Director Angie Steelman said TxDOT will need to survey the work, and the project includes land acquisition that will take time. Additionally, the project includes storm sewer adjustments, adjustments of traffic signals at Butler Road and more, according to city documents.