Check out three ongoing and upcoming road project updates in League City.
Upcoming projects
Package 8 asphalt reconstruction
Project: Package 8 is set to tentatively include asphalt rehabilitations for Bern Street, Boden Street, Austin Street with possible add-on alternates on Seventh Street and Landrum.
Update: A contract awarded at the end of April for construction with it slated to start in June, city officials said.
- Timeline: slated to wrap at the end of 2026
- Cost: $1.74 million
- Funding source: city’s reinvestment cash fund
Ongoing projectsClear Creek Avenue asphalt rehab
Project:
This project will include reconstruction of the road from East Walker Street to East Galveston Street.
Update: The project is currently under construction, city officials said.
- Timeline: slated to wrap by end of June
- Cost: $365,013
- Funding sources: Community Development Block Grant and city cash as needed
Reconstruction of Butler Road and Turner StreetProject: The project is being carried out in two phases and involves roadway improvements and reconstructing the asphalt roadway, as well as waterline work.
Update: Construction is currently ongoing. However, the new Turner Street is open to traffic, city officials said.
- Timeline: slated to fully wrap in the fall
- Cost: $6.12 million
- Funding source: city’s reinvestment fund