Read about some of the latest updates on road and capital projects in League City. This list is not comprehensive.
Package 8 Asphalt Reconstruction
Project: “Package 8” is set to tentatively include asphalt rehabilitations for Bern, Boden and Austin streets, with possible add-on alternates on Seventh Street and Landrum Avenue.
Update: The project has not yet gone out for bid.
- Timeline: bid in spring 2026 and construction in summer 2026
- Cost: estimated to cost $1.85M, but may have to phase construction due to budget constraints
- Funding source: city reinvestment cash fund
FM 518 at Country Lane intersection Improvements
Project: This is a full intersection rebuild at FM 518 and Country Lane, including signal upgrades, mast arm installation and safety enhancements.