Officials in Bastrop County are advancing a range of transportation projects to streamline traffic, safeguard drivers and pedestrians, and meet the demands of a growing population.
This list is not comprehensive.
Upcoming projects
290 extension project
Project: The Central Texas Regional Mobility Authority is reducing congestion along 15 miles of Hwy. 290 between Hwy. 130 and Hwy. 95 South.
Update: A public survey concluded Oct. 10.
- Timeline: expected to complete first draft of schematic design mid-2026
- Cost: TBD
- Funding source: TBD
FM 812 improvement project
Project: The Texas Department of Transportation is upgrading FM 812 to improve safety and reduce congestion, and to improve mobility.
Update: The project spans from US 183 in Travis County to Hwy. 21 in Bastrop County.
- Timeline: expected to finalize design plans in spring 2026
- Cost: $145 million
- Funding source: Texas State Highway Fund
Hwy. 21 improvement project
Project: TxDOT is expanding approximately 7 miles of Hwy. 21 from County Road to Old Highway 20.
Update: Preliminary plans are for the corridor to become a four-lane divided highway with a grassy median.
- Timeline: schematic design and environmental study underway
- Cost: TBD
- Funding source: TBD
Ongoing projects
Blakey Lane extension
Project: The city of Bastrop is extending Blakey Lane from Edward Burleson Lane to a proposed street called Reed Way, south from Reed Way to an intersection at Old Austin Highway, with roundabout options.
Update: The planning stage is 56% complete.
- Timeline: scheduled to begin construction May 25
- Cost: $7 million-$8 million
- Funding source: transportation impact fees, roadway maintenance fees, and water and wastewater fees
Farm, Linden and Water streets improvements
Project: The city of Bastrop is reconstructing pavement along the primary sections of Farm, Linden and Water streets in Bastrop, including:
- Farm Street from Main Street to Wilson Street and from Main Street to Pecan Street
- Water Street from Chestnut Street to Gutierrez Street, from Cedar Street to north of Elm Street, and from Cedar Street to Chestnut Street
- Linden Street from Carter Street to Pecan Street and from Pecan Street to Hill Street
Update: Striping activities began Feb. 13, and Water Street is expected to be completed Feb. 17.
- Timeline: construction began in November
- Cost: $4.36 million
- Funding source: certificates of obligation series 2022 and 2023
Hwy. 71 and Tucker Hill Lane intersection improvements
Project: TxDOT is converting a signalized intersection at Tucker Hill Lane into a grade-separated overpass and constructing new one-way frontage roads.
Update: A groundbreaking ceremony was held Oct. 28.
- Timeline: 2025-28
- Cost: $58.5 million
- Funding source: Texas State Highway Fund
Old Iron Bridge rehabilitation
Project: The city of Bastrop is rehabilitating the Old Iron Bridge to include a concrete deck, steel truss components, railing and decorative lights.
Update: Eastbound traffic on the Loop 150 bridge is closed to accommodate equipment needed for the rehabilitation.
- Timeline: expected to finish construction Sept. 11
- Cost: $9.6 million
- Funding source: certificates of obligation series 2018, 2023 and 2025