Learn more about bond-funded construction projects in Bastrop ISD, based on the district's most recent construction report.
What happened?
BISD Director of Construction and Planning Lee Raspberry provided an update on several bond-funded projects throughout the district in a Jan. 20 board meeting.
Some of the projects are nearing completion, he said.
The details
1. Mina Elementary Phase 2
- Schedule: January 2025-May 2026
- Scope of work: 35,500-square-foot campus expansion
- Status: 78% complete
2 and 3. Bastrop and Cedar Creek Middle School expansions
- Schedule: December 2024-January 2025
- Scope of work: 21,000-square-foot addition to each campus
- Status: 96% complete
4. Riverside Middle School
- Schedule: October 2024-January 2025
- Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities
- Status: 98% complete
5. Creekside Middle School
- Schedule: October 2024-January 2025
- Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities
- Status: 98% complete
6. Bastrop High School
- Schedule: May 2025-December 2027
- Scope of work: 38,000-square-foot addition in permitting phase, new classroom wing and continued renovations
- Status: 25% complete
7. BISD police and operations facility
- Schedule: January 2025-March 2026
- Scope of work: 55,000-square-foot facility to serve police administration, maintenance, custodial, groundskeeping, warehouse and the district’s print shop
- Status: 84% complete