Curious about which new businesses, restaurants and facilities are coming soon or currently underway in your backyard and beyond? Our commercial project round-up helps identify what is being built in your community. The following commercial permits have been filed recently in Round Rock under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.

Boot Barn: 120 Sundance Parkway, Stes. 300 & 350, Round Rock

Type of work: renovation/alteration

Estimated cost: $350,000

Timeline: Oct. 10-Dec. 19


Scope of work: tenant interior finish to include new wall finishes, fixtures and paint

Lewis-Blessing Offices: 2506 CR 172, Round Rock

Type of work: new construction

Estimated cost: $1.25 million


Timeline: Sept. 15, 2022-May 15, 2023

Scope of work: one-story office building

Bowman Park Improvements: 950 E. Bowman Road, Round Rock

Type of work: renovation/alteration


Estimated cost: $295,000

Timeline: Jan. 9, 2023-April 30, 2023

Scope of work: improvements in the project will include replacement of decomposed granite path with concrete, quarry block fence barriers streetside, 1/3 mile of new 5-foot-wide concrete path, benches, natural turf and streetside trees

Claire’s: 4401 N. I-35, Ste. 279, Round Rock


Type of work: renovation/alteration

Estimated cost: $70,000

Timeline: Oct. 24, 2022-Jan. 24, 2023

Scope of work: new door to separate sales/stock, new slat walls, paint walls, new cash wrap tied to existing circuits, new 2x4 lights, new perimeter LED track lighting; no mechanical, plumbing or fire suppression


My Salon Suite: 2711 LaFrontera Blvd., Ste. 110, Round Rock

Type of work: renovation/alteration

Estimated cost: $725,000

Timeline: Sept. 19, 2022-Jan. 13, 2023

Scope of work: interior remodel of an existing tenant suite for use as a hair salon



Baylor Scott & White Round Rock Hospital NICU: 300 University Blvd., Round Rock

Type of work: additions to existing building

Estimated cost: $3,270,968

Timeline: Oct. 24, 2022-Sept. 2, 2024

Scope of work: package includes the NICU core and shell expansions; the core and shell package will include mechanical, electrical, plumbing and other related utilities in preparation for the interior build-out

Baylor Scott & White Round Rock Hospital surgery expansion: 300 University Blvd., Round Rock

Type of work: additions to existing building

Estimated cost: $18,273,787

Timeline: Oct. 24, 2022-Sept. 2, 2024

Scope of work: package includes the core and shell expansions to the surgery and emergency department; core and shell package will include mechanical, electrical, plumbing and other related utilities in preparation for the interior build-out

Baylor Scott & White Round Rock Hospital bed tower: 300 University Blvd., Round Rock

Type of work: additions to existing building

Estimated cost: $43,582,177

Timeline: Oct. 24, 2022-Sept. 2, 2024

Scope of work: package includes the bed tower core and shell expansions; core and shell package will include mechanical, electrical, plumbing and other related utilities in preparation for the interior build-out

Baylor Scott & White Round Rock Hospital Central Utility Plant: 300 University Blvd., Round Rock

Type of work: additions to existing building

Estimated cost: $20.5 million

Timeline: Oct. 24, 2022-Sept. 2, 2024

Scope of work: Central Utility Plant expansion and renovation includes an addition to the electrical switchgear room, a workshop space, medical gas, vacuum and other related utilities

Bank of America: 2651 S. I-35, Round Rock

Type of work: renovation/alteration

Estimated cost: $1.1 million

Timeline: May 1, 2023-Nov. 1, 2023

Scope of work: emergency exterior renovation due to tornado damage including roof and canopy repair along with interior renovation with new furniture, finishes, fixtures, power, data and mechanical, electrical and plumbing; new restrooms and employee break room