Spacecraft manufacturer SpaceX is underway with several Project Echo developments in Bastrop County.

The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.

Breakroom: 858 FM 1209, Bastrop
  • Type of work: additions to an existing building
  • Timeline: Nov. 21, 2023-April 10, 2024
  • Estimated cost: $250,000
Wastewater treatment plant expansion: 858 FM 1209, Bastrop
  • Type of work: new construction
  • Timeline: Nov. 21, 2023-Feb. 29, 2024
  • Estimated cost: $1 million
East parking lot: 858 FM 1209, Bastrop
  • Type of work: new construction
  • Timeline: Nov. 1, 2023-April 3, 2024
  • Estimated cost: $2 million
Shell building: 858 FM 1209, Bastrop
  • Type of work: new construction
  • Timeline: Oct. 1, 2022-Nov. 1, 2023
  • Estimated cost: $43 million
Echo building: 858 FM 1209, Bastrop
  • Type of work: new construction
  • Timeline: Dec. 5, 2022-Sept. 11, 2023
  • Estimated cost: $2 million