Lindsay Road is being restricted to one lane in each direction between Pecos and Germann roads.

The restriction, which began March 9, is in conjunction with the interchange being built at Lindsay and the Loop 202-Santan Freeway. It will last through the duration of the projection, which is scheduled to be completed in March 2022.

The interhcnage will provide freeway access and a frontage road on the freeway’s north side between Lindsay and Gilbert roads.

The $18.15 million project is funded from town of Gilbert bonds and funds, Maricopa Association of Governments funds and developer contributions.