Drivers are advised to slow down and use caution when driving in the area. It affects both eastbound and westbound traffic.
The closures are to facilitate a Salt River Project pole relocation. It is an early part of an $18.15 million construction project to build an interchange at Lindsay and the Loop 202.
Construction for the interchange is anticipated to start in January and be completed in November 2021.
Funding is coming from town of Gilbert bonds and funds, Maricopa Association of Government funds aand developer contributions.