Gilbert Road project moves toward paving on east side of street

0

The town is conducting a major reconstruction of deteriorated asphalt pavement on Gilbert Road from Baseline Road to north of Guadalupe Road.

Construction of the lateral water lines is moving north from Houston Road to Baseline Road. The town anticipates that will be complete by the end of April.

Roadway reconstruction started April 3 in the right lane north from Guadalupe to Baseline. The town anticipates that paving of the east side of Gilbert Road, from north of Guadalupe to just south of Baseline Road, will take place in mid-May.

Concrete crews continue work in the project area to reconstruct driveways in preparation for reconstruction of the roadway.

The project began in November and is expected to run through late August. The cost is $6.15 million funded by the town of Gilbert.

Share this story
COMMENT

Leave A Reply

Tom Blodgett
Raised in Arizona, Tom Blodgett has spent 30 years in journalism in Arizona and is the editor of the Gilbert edition of Community Impact Newspaper. He is a graduate of Arizona State University, where he now serves as an instructional professional in the Walter Cronkite School of Journalism and Mass Communication and editorial adviser to The State Press, the university's independent student media outlet.