The two-phase project spans from FM 1488 to Hufsmith-Conroe Road in Magnolia, widening FM 2978 from two to four lanes. Hardin Store Road is approximately the dividing line for the segments.
Timeline: January 2018-fourth quarter 2019 (south segment), September 2018-second quarter 2021 (north segment)
Cost: $34.2 million
Funding source: Texas Department of Transportation

Share this story
1 comment
COMMENT
  1. There is nothing new in this story that had not been shared many months ago. I would be exited to know what progress has been made so far? Are portions of the FM2978 widening project about to be completed? Are any new businesses (store, restaurants) looking to build along FM2978 as portions of the widening project progresses?

Leave A Reply

Anna Lotz
Anna joined Community Impact Newspaper as a reporter in May 2016 after graduating with a degree in journalism from Cedarville University in Cedarville, Ohio. In July 2017, she transitioned to editor. Anna covers education, local government, transportation, business, real estate development and nonprofits in the Tomball and Magnolia communities. Prior to CI, Anna served as editor-in-chief of Cedars, interned with the National Journalism Center in Washington, D.C., and spent time writing for the Springfield News-Sun and Xenia Daily Gazette.
Back to top