Fort Bend County Engineer Grady Mapes gave updates on several major countywide construction projects at a Texas Department of Transportation Business Roundtable presentation Friday morning at the Rosenberg Civic Center. Check out the list below for the latest on these major road projects.

Road projects happening on I-69 between the Grand Parkway and Reading Road

The $156 million project that runs along I-69 from the Grand Parkway to Reading Road began in 2014 and is set for completion by early 2019. Here are three key updates within the project:

  1. Williams Way Boulevard under I-69 will be re-opened Aug. 24


Williams Way was closed on June 2. Traffic was switched up onto the new I-69 bridge on June 18. Currently, a Williams Way intersection is being built underneath I-69, and Williams Way will be reopened Aug. 24.

  1. Traffic switch at FM 762 to take place in August


A new southbound frontage road will be used to shift traffic to FM 762. The remaining pavement where the existing FM 762 exit traffic is in the process of being completed and a new dedicated exit lane will be added.

  1. Reading Road to close February 2018 for new overpass


Construction on an overpass at Reading Road is scheduled to begin in February 2018 and be completed by May 2018. The project will redirect Reading Road down off I-69 to become an at-grade intersection. Construction will not start until early next year due to holiday shopping that is expected at nearby town shopping centers.




4 construction projects happening on Hwy. 90A

  1. Hwy. 90A at FM 359 elevated overpass


An elevated intersection at Hwy. 90A and FM 359 will form over the Union Pacific Railroad tracks. The $24.5 million project began in June 2016 and is scheduled for completion in May 2019.

  1. Hwy. 90A BNSF Railroad overpass


This $18.4 million project consists of constructing an overpass over the BNSF railroad tracks at the Richmond/Rosenberg city limits. The project will begin in late 2017 and is scheduled to be complete within 36 months. The project has been put on hold because construction crews are waiting on confirmation from AT&T personnel.

  1. Hwy. 90A and FM 1640 crossover to open Aug. 2


This $4.5 million project runs from Frost to Millie streets and started construction late last year. Construction crews have plans to open the crossover between Damon and Louise streets next week, but that date is tentative. Traffic now runs four lanes each direction.

  1. Hwy. 90A at Hwy. 36 railroad overpasses


This project is awaiting work authorization and includes constructing a bridge over the railroad tracks on Hwy. 90A and Hwy. 36. The project cost is $25 million and has a scheduled duration of 27 months. There are two existing railroad passes under Hwy. 90A and Hwy. 36, and when the project is completed overpasses will be constructed over the railroad tracks. The area around Hwy. 36 is prone to flooding; because of this, the project was delayed and will not start until the fall.




3 widening projects to keep an eye out for:

  1. FM 2218 widening


This project runs from Hwy. 59 to SH 36 and is still in the design phase. It is not scheduled to go to bid until fall 2018. The project is estimated to cost $36 million and take three years to complete. The widening will include changing the roadways from asphalt to concrete.

  1. Hwy. 36 widening


This project is still in the design phase and consists of two different segments that will run from north of FM 2218 to the Fort Bend/Brazoria County line.

  • Segment 8 of the project will run north of FM 2218 to Needville-Fairchilds and will cost $70 million. The tentative letting date is set for September 2018 with a construction duration of 40 months.

  • Segment 9 runs from Needville-Fairchilds to the county line and will cost about $45 million. The tentative letting date for segment 9 is November 2018 with construction duration estimated at 16 months.



  1. I-10 widening


This project involves the reconstruction of I-10 from Brookshire to the Brazos River. Currently, I-10 consists of two lanes that run in each direction. Widening I-10 to three lanes will help with congestion that typically forms at the start and end of the weekend for people traveling to San Antonio.

Mapes said lane closures are inevitable but once the project is done, three lanes will run along I-10 to San Antonio. TxDOT's Houston District will be responsible for the project up until Columbus, and the San Antonio District will take on the project from Columbus to San Antonio.