US 380 widening

Texas Department of Transportation continues work on the second phase of the US 380 widening project. The road is being widened to six lanes from Lovers Lane to CR 26 with overpasses at Preston Road and Dallas North Tollway.

A future phase will widen the roadway between CR 26 and Loop 288. This will eventually include overpasses at FM 423, Teel Parkway and Legacy Drive.

Timeline: September 2015-March 2019 (second phase), TBD (third phase)
Cost: $60 million (second phase), TBD (third phase)
Funding source: TxDOT

All information on this page was updated as of 11/27/18. News or questions about these or other local transportation projects? Email us at frsnews@communityimpact.com.

Share this story
COMMENT

Leave A Reply

Nicole Luna is the Senior Reporter for Frisco. She covers development, transportation, education, business and city government. She has a bachelor's degree in Journalism and Spanish from The University of Texas at Arlington and has been with Community Impact Newspaper since June 2015.
Back to top