Transportation update: Construction to widen US 380 to be complete by end of 2018

0

US 380 widening

Work on US 380 between Lovers Lane and CR 26 is expected to be finished by the end of the year. The road is being widened to six lanes with overpasses at Preston Road and the Dallas North Tollway.

The next phase of the project will widen the roadway between CR 26 and Loop 288. That phase will include overpasses at FM 423, Teel Parkway and Legacy Drive.

Timeline: September 2015-December 2018
Cost: $60 million
Funding source: Texas Department of Transportation

Share this story
COMMENT

Leave A Reply

Lindsey Juarez
Lindsey has been involved in newspapers in some form since high school. She graduated magna cum laude from the University of Texas at Arlington in 2014 with a degree in Journalism. While attending UTA, she worked for The Shorthorn, the university's award-winning student newspaper. She was hired as Community Impact Newspaper's first Frisco reporter in 2014. Less than a year later, she took over as the editor of the Frisco edition. Since then, she has covered a variety of topics and issues important to the community, including the city's affordable housing shortage, the state's controversial A-F school accountability system and the city's "Bury the Lines" efforts.
Back to top