Dallas Parkway expansion

Construction of the second phase of the Dallas Parkway widening project began in January. The project will add a lane to the southbound and northbound frontage road at Lebanon Road. The third and fourth phases of the project will begin this summer and will add lanes to Eldorado and Panther Creek parkways.

Timeline: January 2017-September 2018 (Phase 2), July 2018-December 2019 (Phase 3 and 4)
Cost: $11.9 million (Phases 1 and 2), $5.1 million (Phase 3), $2.3 million (Phase 4)
Funding sources: city of Frisco, Collin County, TxDOT