  1. A new Post Road bridge replaced the one destroyed by flooding in 2015, giving drivers another way to connect between San Marcos and Kyle instead of using I-35. Construction was completed on budget and ahead of schedule.
    Date completed: Dec. 20

2. The four-lane overpass on Hwy. 123 over Wonder World Drive in San Marcos was constructed to address safety and mobility, according to TxDOT, which managed the project. The overpass costs $11.6-million.
Date completed: March 20

3. Reconstruction of the 1-mile portion of Bunton Creek Road from I-35 to Lehman Road in Kyle is substantially completed and was funded through the city’s 2013 bond issuance. The project used $3.8 million of the bond funds.
Date completed: August

4. Goforth Road was expanded to include two to three lanes in areas between I-35 and Bunton Creek Road. Construction began in April 2016. The $6.6 million project was funded through Kyle’s 2013 bond issuance and is substantially complete.
Date completed: August

COMMENT

Leave A Reply

Marie Albiges
Marie Albiges is the editor for the San Marcos, Buda and Kyle edition of Community Impact Newspaper. She covers San Marcos City Council, San Marcos CISD and Hays County Commissioners Court. Marie previously reported for the Central Austin edition. Marie moved to Austin from Williamsburg, Va. in 2016 and was born in France.