All information on this page was updated as of 7/30/18.



ONGOING PROJECTS
1. I-35 at FM 3406 improvements
The FM 3406 bridge over I-35 reopened in June. Texas Department of Transportation officials say drivers can expect frontage road changes at FM 3406 as crews work on opening two new U-turn bridges in August.

Timeline: November 2016-fall 2018

2. I-35 access improvements
Final paving work is underway at the intersection of Hwy. 79 and the I-35 frontage roads, and crews are finishing rail work on ramps.

Timeline: July 2016-spring 2019





Recent updates
3. McNeil Road extension
At its completion, the project will serve as a bypass road for downtown Round Rock to improve the flow of traffic, reduce travel times and lower traffic accidents.

Status: Crews will begin preparing the subgrade on the McNeil Road extension and will begin work on curb and gutter installations. The portion of East Bagdad Avenue from Burnet Street to Sheppard Street remains closed.

Timeline: March 2018-spring 2019
Cost: $4.25 million
Funding source: Round Rock’s Transportation and Economic Development Corp. funds

4. CR 119 extension
This project is a roadway extension for CR 119/Ed Schmidt Boulevard from Limmer Loop to Chandler Road in Hutto that will build a four-lane roadway and a traffic signal at CR 119 and Limmer Loop.

Status: Crews placed flexible base on sections of the project in late July. Work continues on roadway pavement, which allows for expansion work.

Timeline: December 2017-early 2019
Cost: TBD
Funding source: Williamson County





UPCOMING PROJECTS
5. Railroad quiet zones, Phase 1
This project will create railroad and street intersections that eliminate the need for train horns inside the city limits of Round Rock. When trains pass, motorists will be prevented from crossing railroad intersections through the additions of medians and four crossing arms. Additionally, red flashing lights will trigger more quickly than at traditional railroad crossings.

Status: Union Pacific Corp. crews will begin their work this month within the company’s right of way. An exact date for the commencement of work has not yet been set, according to city of Round Rock officials.

Timeline: August 2018-winter 2019
Cost: $3.1 million
Funding sources: city of Round Rock, federal grants

6. Limmer Loop sidewalk project
The Limmer Loop sidewalk project will add sidewalk, connecting Cottonwood Creek  Elementary School to FM 1660 North in Hutto. The construction project includes a sidewalk, ramps, drainage structures, pavement markings and signage.

Status: Construction work began June and is split into four phases. Hutto officials say crews are coordinating on utility work.

Timeline: June-fall
Cost: $1.2 million
Funding sources: federal grants, TxDOT funds






NEW TRAFFIC PATTERN
7. RM 620 widening
Williamson County and TxDOT officials on July 23 cut a ribbon to open the new six-lane RM 620. The new widened highway segment stretches 2.74 miles from Cornerwood Drive to Deep Wood Drive and includes a raised median and curb-and-gutter improvements.






NEW TRAFFIC SIGNAL
A. CR 110 at Hwy. 79
Status:
under construction

B. Limmer Loop at Ed Schmidt Blvd.
Status:
under construction






Recent updates
1. Railroad Avenue pavement rehabilitation
This repaving project includes plans to restripe the road from Pfennig lane to Wilbarger Street.

Status: Work has begun on the priority section spanning from Pfennig Lane to Brookhollow Drive. Construction includes resurfacing, temporary striping and reconfiguring the intersection.

Timeline: July-December
Cost: $759,813
Funding source: city of Pflugerville general fund

2. Weiss Lane improvements
The Weiss Lane project will replace all bridges from East Pecan Street to Cele Road starting with the one-lane bridge near East Pecan. It will also expand the roads from two lanes to four with turn lanes, shoulders, drainage improvements, curbs and gutters.

Status: Crews are focusing on the northernmost section of Weiss. The southbound lanes will soon be prepared for construction, which includes storm sewer, curb and gutter, bridge work and widening the roadway into two lanes.

Timeline: March 2017-fall 2018
Cost: $14.6 million (city of Pflugerville), $7.4 million (Travis County)
Funding sources: city of Pflugerville, Travis County

3. East Pflugerville Parkway Reconstruction Project Phase 2
Pflugerville will reconstruct a portion of East Pflugerville Parkway from Colorado Sand Drive to Becker Farm Road, turning the road into a two-lane urban street that will ultimately become a four-lane street.

Crews will lay approximately 4,400 linear feet of new asphalt during construction, and a pedestrian pathway will be built as well.

Status: The city of Pflugerville has closed the road from Becker Farm to Colorado Sand. Crews are laying asphalt.

Timeline: May-August
Cost: $2.675 million
Funding source: city of Pflugerville bonds





UPCOMING PROJECTS
4. SH 130 widening, Segment 2
This project will add a third lane to both directions of the toll road from SH 45 N to US 290, with additional entrance and exit ramp construction.

Status: Construction is expected to start in September.

Timeline: September-summer 2020
Cost: $36.7 million
Funding source: Central Texas Turnpike System






NEW TRAFFIC SIGNAL
A. Heatherwilde Blvd. at New Meister Lane
Status:
operational