TRANSPORTATION: 10 Round Rock, Pflugerville and Hutto projects to know in April

The CR 110 middle project will upgrade the existing two-lane section of CR 110 from north of Limmer Loop to CR 107 to a three-lane roadway. CR 110 is ultimately designed to become a six-lane roadway.

The CR 110 middle project will upgrade the existing two-lane section of CR 110 from north of Limmer Loop to CR 107 to a three-lane roadway. CR 110 is ultimately designed to become a six-lane roadway.

Updates on lane closures, repaving work, road extensions and other transportation projects in Round Rock, Pflugerville and Hutto.



Round Rock & Hutto








Ongoing projects


1. Railroad quiet zones, Phase 1
This project will create railroad and street intersections with electronic signals that eliminate the need for train horns inside Round Rock city limits. Union Pacific Railroad has installed new signals at A Burnet Street and B Williams Street, though both are currently inactive. The city will proceed with median work, curb work and the installation of a traffic signal at Williams. Construction should begin by late May on the city’s portion of the project and will continue through the summer.

Timeline: September 2018-winter 2019

2. Co-Op District road work
Several improvement projects are underway for streets surrounding the Co-Op District, a mixed-use development in Hutto. The city and the Texas Department of Transportation are under an agreement for Hwy. 79 improvements. MA Partners, the developers behind the Co-Op District, are constructing roads inside the development. Short Street closed permanently to motorists in January. City officials advise motorists to use West Street as an alternative route for downtown traffic.

Timeline: fall 2018-summer 2019





Recent updates


3. McNeil Road extension, Phase 2
At completion, the project will serve as a bypass for motorists traveling from downtown Round Rock to improve the flow of traffic, reduce travel times and lower traffic accidents. All connections of Phase 1 are complete, including the McNeil Road extension and McNeil’s connection to Lampasas Street.

Phase 2 of the project will extend A McNeil from Burnet Street to Georgetown Street. B Lewis Street will be extended to connect to McNeil, and improvements are designed for Georgetown Street.

Status: Design plans for Phase 2 are complete. The project is anticipated to go to bid in April.
Timeline: TBA
Cost: TBA
Funding source: Round Rock Transportation and Economic Development Corp. funds







4. CR 110 middle
This project will upgrade the existing two-lane section of CR 110 from north of Limmer Loop to CR 107 to a three-lane roadway. CR 110 is ultimately designed to become a six-lane roadway.

Status: A ceremonial ground breaking scheduled for March 15 was postponed. However, the county has completed its right of way acquisitions. Utility relocations are underway.
Timeline: April 2019-spring 2020
Cost: $8.91 million
Funding source: Williamson County





Upcoming projects


5. FM 1660 intersection improvements
Three FM 1660 intersections— A North FM 1660 at Limmer Loop, B FM 1660 at Highway 79 and C South FM 1660 at Front Street—were included in the city of Hutto’s 2018 transportation bonds. The intersection improvements are designed to mitigate backups within Hutto city limits.

Status: The city is negotiating with the project’s engineer. Following negotiations, the city will coordinate with TxDOT and begin preliminary engineering, which includes traffic counts, utility exploration, environmental assessment and other studies. This process will take several months, according to city spokesperson Eliska Padilla.
Timeline: TBD
Cost: $6 million
Funding source: 2018 transportation bond funds

6. Red Bud Lane improvements
Improvements are planned for Red Bud Lane from Palm Valley Boulevard to Pioneer Crossing Drive. On the northbound side, crews will construct a raised median and a right-turn lane into the north entrance of the Walmart parking lot. On the southbound side, plans include construction of a dedicated right-turn lane, one straight lane and two dedicated left-turn lanes.

Status: The design of the project is complete, and the city opened an engineering bid for the project March 12.
Timeline: TBD
Cost: $600,000
Funding source: budgeted/Type B

7. University Boulevard widening
This project will widen A University Boulevard to a six-lane, median-divided arterial from the North I-35 frontage road to Sunrise Road. Dual turn lanes will be installed at the intersections of B Oakmont Drive and C University Oaks Boulevard.

Status: Utility relocation has begun on the project, according to Round Rock city officials.
Timeline: project to go to bid by late 2019 or early 2020
Cost: TBD
Funding source: TBD

8. Highway 79 crossing

Status: The city of Hutto is in the process of selecting a contractor for a possible overpass or underpass that would bypass Highway 79. Hutto City Engineer Matt Rector and Jessica Romigh, chair of the Hutto planning and zoning commission, recommended to Hutto City Council a way over or under the highway as a means to connect the northern and southern sections of the city.

Hutto City Manager Odis Jones directed staff to begin design work on the project. Preliminary plans show the connector located between CR 132 and CR 134 near Highway 79. The overpass/underpass would connect to CR 132 north of Highway 79.
Timeline: TBD
Cost: TBD
Funding source: 2018 transportation bond funds






Pflugerville








Ongoing projects


1. Heatherwilde/Windermere neighborhood repair
The first four phases—including sidewalk, curb, gutter, driveway and street reconstruction—are complete. Road reconstruction and concrete work continues in the final two phases, both of which are within the Heatherwilde neighborhood. Weather permitting, roadway reconstruction on streets—including Cactus Blossom Drive, Ardisia Drive and Dashwood Creek Drive—will take place in late spring.

Timeline: March 2018-June 2019

2. Weiss Lane improvements
Work continues on Weiss Lane. Recent areas of work include paving between A Pflugerville Parkway and Pecan Street as well as traffic signals at the road’s intersections with B Pflugerville Parkway and Wolf Pack Drive. When complete, the Weiss Lane project will replace all bridges from East Pecan Street to Kelly Lane. The project will also expand the road from two to four lanes with turn lanes, shoulders, drainage improvements, curbs and gutters. Drivers are advised to watch for lane shifts.

Timeline: March 2017-June 2019





Recent updates


3. Pfennig Lane widening and reconstruction
The project, currently under construction, will reconstruct and widen Pfennig Lane to a three-lane roadway with curbs and gutters from Rocky Creek Drive to Justice Center Drive. Designs for the project include one lane in either direction with a center turn lane.

Status: Pfennig will be reduced to one lane of westbound traffic while the city works on the first phase of the project, which includes improvements to the southern part of the road. Eastbound traffic through this portion of Pfennig will detour through East Pflugerville Parkway and FM 685. One-way traffic patterns will continue for the duration of the project.
Timeline: March 2019-winter 2019
Cost: $1.62 million
Funding source: 2014 city of Pflugerville transportation bonds

4. SH 130 widening
The first segment of the SH 130 widening project will ultimately add a third lane to both the northbound and southbound portions of the toll road from SH 45 N. to US 290 with additional entrance and exit ramp construction. Crews broke ground on the project October 4.

Status: Crews are working at the Parmer and Howard lanes and Gilleland Creek bridges. Half of the drill shafts at the Gilleland bridge are now complete. Beams are scheduled to be installed at the Parmer bridge later this spring. Excavation and embankment for the third travel lane are taking place between Highway 290 and Howard.
Timeline: October 2018-late 2020
Cost: $36.7 million
Funding source: Central Texas Turnpike System





Upcoming projects


5. Old Austin-Hutto Road improvements
This project will widen Old Austin-Hutto Road into a three-lane divided roadway and improve pavement. Design plans are mostly complete and include improvements for curb and gutter, drainage and a low-water crossing.

Status: Construction on the project is anticipated to begin in late summer 2019, according to city officials. A ground breaking is pending on updates for design and determination of the construction schedule.
Cost: $4.01 million
Funding source: 2018 city of Pflugerville bonds




MOST RECENT

A sign directs voters inside Ridgetop Elementary School in North Central Austin. (Jack Flagler/Community Impact Newspaper)
11.8% of voters in Travis County have voted early since June 29, exceeding 2018 primary numbers

More than 97,000 Travis County residents have voted in person or by mail. The turnout far surpassed the combined early and Election Day totals in the 2018 primary run-off election.

A photo of the potential Tesla property
Travis County updates Tesla incentive package, pushing for $1 billion-plus investment from the company

Poised for a possible July 13 vote, Travis County has released a refined incentives structure proposal with electric carmaker Tesla.

The Williamson County and Cities Health District confirmed 37 additional coronavirus cases July 10, bringing the total to 3,654. (Community Impact Staff)
37 new cases of coronavirus, 1 death confirmed in Williamson County on July 10

Currently, 103 patients are hospitalized, 32 are in intensive care and 16 are on a ventilator.

The species that tested positive for West Nile Virus is Culex quinquefasciatus, or the southern house mosquito. This species has a flight range of about one mile. ​(Courtesy Adobe Stock)
Mosquitoes test positive for West Nile Virus near southwest Williamson County Regional Park

There have been no reported human cases of West Nile Virus in Williamson County since 2017.

Williamson County sees 844 new coronavirus cases this week

Between July 4 and July 10, Williamson County also reported 9 additional deaths.

Texas Commissioner of Education Mike Morath announced in a June 30 State Board of Education meeting that students will be taking the STAAR in the 2020-21 school year. (Courtesy Pixabay)
Education organizations call for STAAR requirements to be waived another year

Gov. Greg Abbott waived the State of Texas Assessments of Academic Readiness, or STAAR, testing requirements in March of earlier this year in response to the coronavirus pandemic.

With a clinical background in internal, pulmonary and critical care medicine, Corry has been with BCM for 20 years. He now focuses primarily on inflammatory lung diseases, such as asthma and smoking-related chronic obstructive pulmonary diseases. (Graphic by Ronald Winters/Community Impact Newspaper)
Q&A: Baylor College of Medicine's Dr. David Corry discusses immunity, vaccine production amid COVID-19 pandemic

Rapid development and distribution of a vaccine worldwide and successful achievement of herd immunity will be key players in determining the lifespan of the COVID-19 pandemic, said Dr. David Corry, a professor of Medicine in the Immunology, Allergy and Rheumatology Section at Baylor College of Medicine.

Chisholm Trail Road will be closed between RM 620 and Sunset Drive due to utility work scheduled for the RM 620 project. (Courtesy Fotolia)
Chisholm Trail Road in Round Rock to close July 13 through early August for RM 620 work

Chisholm Trail Road will be closed between RM 620 and Sunset Drive due to utility work scheduled for the RM 620 project.

The new partnership will provide on-site, same-day testing and results for assisted-living facility staff and their residents. (Courtesy Adobe Stock)
State announces partnership for increased COVID-19 testing for patients, staff at assisted-living facilities, nursing homes

These test sites will help the state work toward the goal of processing up to 100,000 tests in the first month.

The Brushy Creek Regional Wastewater System Treatment Plant's expansion is an anticipated three-year process that will increase the plant's capacity by 40%. (Taylor Jackson Buchanan/Community Impact Newspaper)
Plans to expand Brushy Creek wastewater plant in Round Rock by 2023 move forward

The consulting agreement approved July 9 would test materials such as concrete, soil and asphalt to ensure that the products are made to the city's specifications.

Former Cedar Park Police Department Chief Sean Mannix is pictured in this 2015 file photo. (Community Impact Newspaper file photo)
Cedar Park police chief moves to Burnet, driver's license offices reopen: Most popular news this week from Central Texas

Read the most popular Central Texas news from the past week on Community Impact Newspaper's website.

A photo of Del Valle ISD's Cardinal stadium
Del Valle ISD approves Tesla incentives, paving way for possible Travis County agreement

The school district's July 9 vote could yield Tesla around $46.4 million in tax abatements if the company chooses Travis County as its next factory site.