TRANSPORTATION UPDATES


1. Parker Road/Dallas Parkway intersection improvements


Street easement acquisitions and utility relocations are underway for a project to add dedicated northbound and southbound right-turn turn lanes along Dallas Parkway at Parker Road.


Timeline: November 2015-June 2016
Cost: $1.3 million
Funding Sources: city of Plano,Collin County




TRANSPORTATION UPDATES Legacy Drive repairs[/caption]

2. Legacy Drive repairs


One- to two- westbound and eastbound lanes along Legacy Drive between Coit Road and Marchman Way are closed for concrete repairs in this multiphase project. The repair work is expected to be complete by April, weather permitting.


Timeline: April 2015-April 2016
Cost: $1.8 million
Funding Sources: city of Plano



3. Park Boulevard/US 75 pedestrian crossing project


Construction to create a 12-foot-wide hike and bike trail from west of Enterprise Drive to the Dallas Area Rapid Transit station at Archerwood Street is nearing completion. The trail connects to the nearby Chisholm Trail.


Timeline: April–November
Cost: $1.4 million
Funding sources: city of Plano, North Central Texas Council of Governments



4. Windhaven Parkway widening


Lane closures will take place on Midway Road and Communications Parkway through mid-December for a project to widen Windhaven Parkway into a six-lane thoroughfare from Gentle Way to Parkwood Boulevard. The project is expected to be complete by April 2016.


Timeline: March 2015-March 2016
Cost: $4.4 million
Funding sources: city of Plano







TRANSPORTATION UPDATESNew Project: Royal Oaks Drive repaving project


Paving is underway on Royal Oaks Drive between Jupiter Road to Spring Creek Parkway where traffic is reduced to one lane. Crews hope to complete the northern portion of the roadway and begin work on the south half of the project by early December.


Timeline: October-January
Cost: $2.2 million
Funding sources: city of Plano