Tabu Shabu: 1620 N. Hardin Blvd., Ste. 1000, McKinney
Type of work: renovation/alteration
Timeline: March 15-June 1
Estimated cost: $200,000
Dave’s Hot Chicken: 4040 W. University Drive, Ste. 100, McKinney
Type of work: renovation/alteration
Timeline: March 1-June 1
Estimated cost: $250,000
Aura McKinney: southeast corner of Stacy Road and Kickapoo Drive, McKinney
Type of work: new construction
Timeline: May 1, 2022-May 1, 2024
Estimated cost: $44 million
Capriotti’s Sandwich Shop: 3194 W. University Drive, Ste. 600, McKinney
Type of work: new construction
Timeline: April 15-July 15
Estimated cost: $325,000
Salad and Go: 4751 S. Custer Road, McKinney
Type of work: new construction
Timeline: June 3-Sept. 5
Estimated cost: $300,000