SH 26 widening


GCS Transportation Updates June SH 26 Phase 2[/caption]

Along SH 26 in Colleyville, motorists can expect to see construction activity continue south of Centerpark Drive, including bridge work at the Little Bear Creek bridge and storm drainage work near Brown Trail and Centerpark. Construction activity throughout the rest of the project will include preparation of the right of way, excavation and storm drainage work on the west side of SH 26 between Centerpark and John McCain Road.


Timeline: November 2016-19
Cost: $38.2 million
Funding source: Texas Department of Transportation



SH 121/SH 360 interchange


GCS Transportation Updates July SH 121/SH 360 interchange[/caption]

Paving crews are still working between north and southbound SH 121 in Grapevine. Grading and drainage work is ongoing on the new northbound SH 360 alignment to westbound SH 114. This summer crews will finish setting the bridge beams on the project and continue working on bridge deck placement on three of the bridges. The new eastbound SH 114 flyover to southbound SH 121 is expected to open at the end of the summer. The current flyover will then be reconfigured for eastbound SH 114 to southbound SH 360.


Timeline: Aug. 30, 2016-2018
Cost: $61 million
Funding source: TxDOT



SH 121 expansion


GCS Transportation Updates June SH 121 expansion[/caption]

Current activities include the reconstruction of the entrance ramp that was closed months ago due to work in the Grapevine Mills Boulevard/Sandy Lake Road bridge area. Concrete paving is upcoming. In July workers will continue concrete paving on the southbound main lanes at the south end of the project. They will continue concrete paving from Grapevine Mills’ bridge to the southern project limits of the northbound side and continue permanent striping where applicable.


Timeline: March 2014-September 2017
Cost: $58.8 million
Funding sources: TxDOT, North Central Texas Council of Governments, federal funds



Glade Road Phase 1A


GCS Transportation Updates July Glade Road Phase 1A[/caption]

Colleyville’s Glade Road project began in June with a focus on Phase 1A, which runs from just west of Bransford Road to SH 26. The project consists of rebuilding the existing road surface, installing a drainage system, a new bridge along Glade west of Bransford, and installing sidewalks and trails along both sides of Glade within the project limits. Crews are preparing the site for a new fiber communication system, placing new storm drains and removing existing asphalt.


Timeline: June-October 2017
Cost: $1.97 million
Funding source: city of Colleyville