Main Street widening
Construction continues to widen Main Street from four lanes to six lanes from Dallas Parkway to FM 423. Crews are currently working on a section between Teel Parkway and Legacy Drive. The project includes installing a water line and underground power lines.

Timeline: October 2017-April 2019
Cost: $27.6 million
Funding sources: city of Frisco, Brazos Electric Cooperative