FM 2499 improvements
The project includes the replacement of an undersized drainage structure under FM 2499 west of the FM 2499/Gerault Road intersection, the installation of a new drainage structure for the existing drainage structure that is being replaced running along the western side of FM 2499 to Denton Creek, and the extension of the flyover lane into Grapevine and FM 2499/Gerault intersection improvements. Crews are currently working on installing drainage improvements. The drainage work is expected to help prevent flooding on the road, which the town has experienced in recent years.

Timeline: December-August 2018
Cost: $8.7 million
Funding sources: town of Flower Mound, state funds






FM 544 widening
Work on FM 544 from FM 2281 to Parker/Dozier Road is 50 percent complete. The road is being widened from a two-lane rural roadway to a six-lane, divided urban curb-and-gutter roadway with a raised median. There are bridges being built that will run over the Kansas City Southern Railroad line and Indian Creek. Crews are currently tying rebar, setting bridge panels and overhangs. They are also preparing to pour the deck on the Indian Creek bridge.

Timeline: summer 2015-October 2019
Cost: $35.3 million
Funding sources: cities of Carrollton and Lewisville, Texas Department of Transportation, Denton County






Waketon Road paving
The contractor is currently finalizing the storm sewer installation. The contractor’s current schedule includes subgrade preparation beginning early February with paving to follow. The contractor anticipates the road opening to traffic in March. The project consists of the upgrade of the existing Waketon Road and Rippy Road asphalt roads located adjacent to the Bradford Parks subdivision to a two-lane urban collector. The temporary northbound lane is installed.

Timeline: summer 2017-March 2018
Cost: $2,763,000
Funding source: town of Flower Mound






Valley Vista subdivision repairs
Residential streets in the Valley Vista subdivision in Lewisville will undergo street and sidewalk maintenance repairs. Acorn Drive from Vista Drive to Cassion Drive as well as Cassion from Little Den Drive to the L section on Cassion are scheduled for repairs in February.

Timeline: late January-February
Cost: TBD
Funding source: city of Lewisville


By Sherelle Black
Sherelle joined Community Impact Newspaper in July 2014 as a reporter for the Grapevine/Colleyville/Southlake edition. She was promoted in 2015 to editor of the GCS edition. In August 2017, Sherelle became the editor of the Lewisville/Flower Mound/Highland Village edition. Sherelle covers transportation, economic development, education and features.


MOST RECENT

picnic tables on turf
400 West Main in Lewisville offers outdoor venue for events

The venue in Old Town Lewisville can host events of up to 250 people.

person in fire fighting suit
Lewisville, Flower Mound and Highland Village collaborate on joint fire training building

Construction of the fire training facility is expected to begin this fall.

smart phone app with van in background
New on-demand shuttle service GoZone approved for Lewisville, Highland Village and Denton

The GoZone service will launch Sept. 7 with 32 vans operated by agreement through a private company called Via.

Peter Lake (left), chair of the Public Utility Commission of Texas, and Brad Jones, interim president and CEO of the Electric Reliability Council of Texas, provided an update on state regulators' electric grid redesign efforts in Austin on July 22. (Ben Thompson/Community Impact Newspaper)
Regulators: Texas electric grid prepared for potentially record-breaking demand next week; 'once-in-a-generation reforms' underway

The heads of the agencies in charge of the Texas electric grid met in Austin on July 22 to provide updates on their grid reform efforts.

trail with trees
Lewisville's new Thrive Nature Park to hold grand opening on Aug. 28

A grand opening for Lewisville's new Thrive Nature Park is set for Aug. 28.

rendering of buildings
Lewisville looking to propose nearly $100M bond measure to fund new public safety complex

The city of Lewisville is poised to call a November bond election to fund a new central police and fire complex.

The Lewisville location of Northern Tool   Equipment will open in its new location July 29. (Courtesy Northern Tool   Equipment)
Northern Tool + Equipment retailer moving to new location in Lewisville to make way for I-35E expansion

Widening of I-35E has required partial demolition of the current location for Northern Tool + Equipment.

building rendering
Lewisville amends economic development agreement on Old Town project

Nack Development has pledged to invest $5 million to construct a three-story building at Main and Charles streets in Lewisville.

sick dog at hospital
Permit approved for new emergency veterinary hospital in Flower Mound

Flower Mound Town Council unanimously approved a specific-use permit July 19 for Prairie Plaza Vet.

Suburban Yacht Club plans to open in Plano in August. (Courtesy Shannon McCarthy)
Suburban Yacht Club coming to Plano; Gidi Bar & Grill opens in Frisco and more DFW-area news

Read the latest business and community news from the Dallas-Fort Worth area.

meeting
Flower Mound looking to create commission to help make community better

The proposal calls for a seven-member commission that would meet bimonthly starting in October.