1.183 South project


This project includes the addition of a three-lane tolled expressway in each direction and improvements to the non-tolled lanes. Workers are laying concrete for the new A. 183 toll lanes and finishing a bridge over the 183 toll road at Loyola Lane. The first section of the 183 toll road from Hwy. 290 to near Techni Center Drive will open later this year.
B. Farther south, major traffic shifts will occur this summer around the Colorado River, as the new non-tolled southbound lanes open between Bolm Road and Thompson Lane.
Timeline: 2016-20
Cost: $743 million
Funding sources: Central Texas Regional Mobility Authority toll revenue bonds, federal loans, Texas Department of Transportation loans






2.New MetroRapid stations


Due to increased ridership and frequency of service, Capital Metro is adding eight new pairs of bus stations along two MetroRapid routes: A. Route 801, which runs on North Lamar Boulevard to Guadalupe Street to South Congress Avenue, and B. Route 803, which runs on Burnet Road to Guadalupe Street to South Lamar Boulevard. By late April, 15 of the 16 new stations had been completed.
Timeline: summer 2018-June
Cost: $1.7 million
Funding source: Capital Metro






3.Guadalupe corridor improvements


The city of Austin and Capital Metro are collaborating to improve traffic flow around the Lavaca Street and Martin Luther King Jr. Boulevard intersections. Construction began in May to establish new bus routes. Buses traveling north on Lavaca will turn left on 18th Street rather than at Martin Luther King. Guadalupe Street is one-way traveling south, so buses will then use a separated contraflow lane to pass north through the intersection with Martin Luther King using a bus-only signal.
Timeline: May-September
Cost: $1.25 million
Funding source: 2016 city of Austin mobility bond






4.Sabine Street promenade


This project is intended to make the area more accessible to bikers and pedestrians and includes sidewalk widening; installation of two-way bike lanes, benches and traffic signals; and improvements to water lines, storm drains and wastewater piping. The city’s contractor finished work on the east side of the 500 block of Sabine Street in mid-May before moving to the west side. Additionally, the contractor is preparing to begin concrete paving for the 500 block.
Timeline: spring 2018-summer 2019
Cost: $2.8 million
Funding sources: 2010 and 2012 city of Austin mobility bonds






5. I-35 improvements at Oltorf Street


This project involves new exit and entrance ramps in the area to allow vehicles to have longer distances to merge off and on the main traffic lanes. In mid-May, TxDOT opened the new permanent southbound I-35 entrance ramp between Oltorf and Woodward streets. Construction of the shared-use path and reconstruction of driveways will continue along the southbound frontage road over the next several weeks.
Timeline: February 2017-mid-2019
Cost: $42.6 million
Funding source: TxDOT


By Emma Freer
Emma Freer began covering Central Austin for Community Impact Newspaper in 2017. Her beat includes the Travis County Commissioners Court and local business news. She graduated from Columbia Journalism School in 2017.


MOST RECENT

The Electric Reliability Council of Texas issued a call for Texans to conserve energy June 14. (Iain Oldman/Community Impact Newspaper)
ERCOT asks Texans to conserve energy with generation outages 2.5 times higher than normal

"This is unusual for this early in the summer season," said Woody Rickerson, ERCOT vice president of grid planning and operations, in a news release.

The rezoning request for the Springdale Green Planned Unit Development passed Austin City Council 10-0 June 10. (Ben Thompson/Community Impact Newspaper)
Rezoning for East Austin's Springdale Green PUD plan passes in unanimous City Council vote

The PUD plan garnered some community resistance this spring due to concerns over how a height increase for the project's proposed office towers could affect development and resident displacement in surrounding neighborhoods.

Austin moved into its second phase of Proposition B ordinance enforcement June 13 and began working to move some campers around City Hall on June 14. (Ben Thompson/Community Impact Newspaper)
Austin Police Department clearing tents around City Hall

The city began issuing written warnings June 13 in its second phase of enforcing criminal penalties for camping in public.

UT Austin football stadium filled with fans
In Austin and the rest of the nation, the business of college sports is changing

If Gov. Greg Abbott signs SB 1325 into law, Texas will join a number of other U.S. states in allowing college athletes to profit off their names, images and likenesses.

Lingering symptoms, long-term impact of COVID-19 will take time to fully understand

Dr. Mary Katherine Theoktisto answers questions regarding the virus.

Salvation Pizza, opening in the Austin-Bergstrom International Airport June 16, is one of several new pizza options in the Austin area. (Courtesy Salvation Pizza)
Pie chart: See a map of 11 new, coming-soon pizza options in the Austin area

New spots include Above Ground Pizza opening in New Bruanfels after several permitting delays and Salvation Pizza feeding travelers at the Austin-Bergstrom International Airport

Austin City Council members finalized their spending plan for the federal stimulus dollars before adjourning for their summer recess that will stretch to late July. (Ben Thompson/Community Impact Newspaper)
Austin will dedicate $100M in federal stimulus funds to combating homelessness over two years

In one of their last detailed discussions before their summer break, council members secured funding for several of their individual priorities alongside homelessness allocations.

Photo of Congress Street
The Moontower Comedy Festival will return in September

Headliners for the four-day festival include Margaret Cho, Dave Attell and others.

The extension of Kenney Fort Boulevard is underway north of Hwy. 79. (Amy Bryant/Community Impact Newspaper)
North-south road in Round Rock makes progress; homestead exemption OK'd in Leander and more Central Texas news

Read the top business and community news from the past week from the Central Texas area.

Candlewood Suites is located at 10811 Pecan Park Blvd., Bldg. 2, Austin. (Chris Neely/Community Impact Newspaper)
Austin City Council votes for improved coordination with local counties on homeless issues; no action taken on Williamson County Candlewood Suites purchase before summer break

Council members unaimously approved a resolution aimed at improving collaboration on homeless strategy between Austin and local county officials June 10.