Dallas Parkway widening construction continues

0

Construction is more than half done on the first phase of the Dallas Parkway project to construct an additional lane on northbound and southbound frontage roads with intersection improvements at Warren Parkway and Lebanon Road. The second and third phases, which will add a lane on the northbound and southbound frontage roads at Eldorado and Panther Creek parkways,  are still in the planning phase.

Timeline: January 2017-December 2018 (Warren Parkway and Lebanon Road), July 2018-TBD (Eldorado and Panther Creek parkways)
Cost: $11.5 million (Warren Parkway and Lebanon Road), $7.5 million (Eldorado and Panther Creek parkways)
Funding sources: city of Frisco, Collin County, Texas Department of Transportation


See all of September’s transportation updates here.