The city of Bastrop is set to acquire $836,610 of land near FM 969 and Blakey Lane.
The details
The land, which Bastrop Assistant City Manager Andres Rosales told Bastrop City Council would be “for the public benefit,” will include the following:
- A permanent waterline easement
- A permanent wastewater easement
- Temporary construction easements
- Expanded right of way
Some background
Bastrop is extending Blakey Lane from Edward Burleson Lane to a proposed street called Reed Way, south from Reed Way to an intersection at Old Austin Highway, with roundabout options.
Construction—estimated to cost $7 million-$8 million and be funded with transportation impact fees, roadway maintenance fees, and water and wastewater fees—is scheduled to begin May 25, according to city documents.
What else?
Blakey Lane is north of Sendero, a 75-acre mixed-use development under construction along Hwy. 71.
Sendero will be developed in multiple phases through 2030, with its first retail and dining openings anticipated this year, according to developer Pearl River Companies.
The cost
The $836,610 will be paid for through the Blakey Land Acquisition Fund, according to city documents.